Novar Wind Farm (Extension) (36.8 MW)

Novar Wind Farm (Extension) is a 36.8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 September 2012; the record was last updated on 4 December 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36.8 MWwind farm
operationalstatus in REPD
4 December 2012record last updated
Highlandcouncil area

Planning timeline

DateStage
14 May 2003Application submitted
20 June 2005Planning permission granted
1 August 2010Construction started
17 September 2012Operational

Project details

Technology
wind farm
Capacity
36.8 MW
Status (REPD)
operational
Record last updated
4 December 2012
Operator or applicant
RWE npower
Planning authority
Highland
Planning application reference
03/00426/FULRC
Turbines
16
Address (REPD)
Novar Estate Evanton Ross-shire
Council area (by location)
Highland
Time to decision
110 weeks
REPD reference
4013

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Meall an Tuirc Wind Farmwind farm17operational<0.1
Bendealt Wind Farm, Highlandwind farm9operational0.5
Clach Liath Wind Farmwind farm42.5refused5.8
Drumore Cottage, Swordalebattery storage49.9approved, not built6.1
Coire Na Cloiche Wind Farmwind farm29.9operational7.4
The Smithybattery storage45approved, not built8.7
Woodlands Wind Farmwind farm15application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.71, -4.427).