Meall an Tuirc Wind Farm (17 MW)

Meall an Tuirc Wind Farm is a 17 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 1997; the record was last updated on 3 December 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17 MWwind farm
operationalstatus in REPD
3 December 2009record last updated
Highlandcouncil area

Planning timeline

DateStage
17 May 1995Application submitted
27 August 1996Planning permission granted
1 September 1997Operational

Project details

Technology
wind farm
Capacity
17 MW
Status (REPD)
operational
Record last updated
3 December 2009
Operator or applicant
RWE npower
Planning authority
Highland
Planning application reference
not recorded
Turbines
34
Address (REPD)
Novar Estate
Council area (by location)
Highland
Time to decision
67 weeks
REPD reference
3297

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Novar Wind Farm (Extension)wind farm36.8operational<0.1
Bendealt Wind Farm, Highlandwind farm9operational0.5
Clach Liath Wind Farmwind farm42.5refused5.8
Drumore Cottage, Swordalebattery storage49.9approved, not built6.1
Coire Na Cloiche Wind Farmwind farm29.9operational7.4
The Smithybattery storage45approved, not built8.7
Woodlands Wind Farmwind farm15application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.71, -4.427).