Coire Na Cloiche Wind Farm (29.9 MW)

Coire Na Cloiche Wind Farm is a 29.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2020; the record was last updated on 23 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWwind farm
operationalstatus in REPD
23 March 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
16 February 2012Application submitted
25 April 2013Planning permission granted
24 August 2017Construction started
1 March 2020Operational

Project details

Technology
wind farm
Capacity
29.9 MW
Status (REPD)
operational
Record last updated
23 March 2020
Operator or applicant
RockbySea
Planning authority
Highland
Planning application reference
12/00479/FUL
Turbines
13
Address (REPD)
Land At Sidhean A'Choin Bhain, Strathrusdale, Alness
Council area (by location)
Highland
Time to decision
62 weeks
Contracts for Difference
AR1
REPD reference
3846

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Beinn Tharsuinn Windfarm Projectwind farm29.8operational4.8
Strathrory Wind Farmwind farm36approved, not built5.1
Torr Leathann, Ardrossbattery storage5refused5.1
Torr Leathann, Ardross Wind Farmwind farm36refused5.1
Meall an Tuirc Wind Farmwind farm17operational7.4
Novar Wind Farm (Extension)wind farm36.8operational7.4
Bendealt Wind Farm, Highlandwind farm9operational7.8
The Smithybattery storage45approved, not built8.8
Glenmorie Wind Farmwind farm134refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.7696, -4.3732).