Strathrory Wind Farm (36 MW)

Strathrory Wind Farm is a 36 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 January 2022, not yet built; the record was last updated on 31 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
approved, not builtstatus in REPD
31 March 2023record last updated
Highlandcouncil area

Planning timeline

DateStage
6 March 2020Application submitted
15 June 2021Refused by the planning authority
30 June 2021Appeal lodged
7 January 2022Planning permission granted
7 January 2022Appeal allowed

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
31 March 2023
Operator or applicant
Energiekontor UK
Planning authority
Highland
Planning application reference
20/00584/FUL
Turbines
7
Turbine height
150 m
Address (REPD)
Land at Strathrory, 4km northeast of Ardross and 8km northwest of Alness
Council area (by location)
Highland
Time to decision
96 weeks
REPD reference
7476

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Torr Leathann, Ardrossbattery storage5refused0.3
Torr Leathann, Ardross Wind Farmwind farm36refused0.3
Beinn Tharsuinn Windfarm Projectwind farm29.8operational5.0
Coire Na Cloiche Wind Farmwind farm29.9operational5.1
The Smithybattery storage45approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.7665, -4.2878).