Energy Projects Near You

Beinn Tharsuinn Windfarm Project (29.8 MW)

Beinn Tharsuinn Windfarm Project is a 29.8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2005; the record was last updated on 11 April 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.8 MWwind farm
operationalstatus in REPD
11 April 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
19 April 2002Application submitted
11 February 2005Planning permission granted
1 May 2005Construction started
1 December 2005Operational

Project details

Technology
wind farm
Capacity
29.8 MW
Status (REPD)
operational
Record last updated
11 April 2011
Operator or applicant
CRE Energy/ Scottish Power
Planning authority
Highland
Planning application reference
RC2003784 & SU2003318
Turbines
17
Address (REPD)
Beinn Tharsuinn,Nr Easter Andross, Easter Ross, Northern Highlands
Council area (by location)
Highland
Time to decision
147 weeks
REPD reference
4669

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Torr Leathann, Ardross Wind Farmwind farm36refused4.7
Torr Leathann, Ardrossbattery storage5refused4.7
Coire Na Cloiche Wind Farmwind farm29.9operational4.8
Strathrory Wind Farmwind farm36approved, not built5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.8053, -4.329).