Solar, wind and battery projects near Bonar Bridge (IV24)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV24 (Highland): 3 are waiting for a planning decision, 1 operational. The largest live scheme is Balblair Wind Farm (36 MW wind farm, application submitted on 14 March 2025, no decision recorded), 2.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
3awaiting a decision
0approved, not running
1operational

Projects within 10 km of IV24

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Balblair Wind Farmwind farmwind farm36application submittedupdated May 2025Mar 2025—May 2025Highland2.3
Balblair Wind Farmbattery storagebattery storage30application submittedupdated May 2025Mar 2025—May 2025Highland2.3
Beinn Tharsuinn Windfarm Projectwind farmwind farm29.8operationalupdated Apr 2011Apr 2002granted Feb 2005Apr 2011Highland9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Inveroykel Wind Farm Batterybattery storagebattery storage—application submittedupdated Apr 2026Feb 2026—Apr 2026Highland4.9

Distance from the average position of the IV24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm2101036
Battery storage2200030

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.