Energy Projects Near You

Solar, wind and battery projects near Tain (IV19)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV19 (Highland): 1 approved but not yet running. The largest live scheme is Shore Road - Distillery and Visitor Centre (1 MW solar farm, approved on 31 October 2023, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of IV19

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cambusmorewind farmwind farm49.5application withdrawnupdated Jun 2010——Jun 2010Highland8.4
Shore Road - Distillery and Visitor Centresolar farmsolar farm1approved, not builtupdated May 2026Jan 2023granted Oct 2023May 2026Highland8.5

Distance from the average position of the IV19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101001
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.