Solar, wind and battery projects near Tain (IV19)
2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV19 (Highland): 1 approved but not yet running. The largest live scheme is Shore Road - Distillery and Visitor Centre (1 MW solar farm, approved on 31 October 2023, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of IV19
Projects of 1 MW and more (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cambusmorewind farm | wind farm | 49.5 | application withdrawnupdated Jun 2010 | — | — | Jun 2010 | Highland | 8.4 |
| Shore Road - Distillery and Visitor Centresolar farm | solar farm | 1 | approved, not builtupdated May 2026 | Jan 2023 | granted Oct 2023 | May 2026 | Highland | 8.5 |
Distance from the average position of the IV19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 1 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Highland decides solar, wind and battery applications
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.