The Smithy (45 MW battery storage)

The Smithy is a 45 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 January 2025, not yet built; the record was last updated on 4 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
approved, not builtstatus in REPD
4 March 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
4 January 2024Application submitted
29 January 2025Planning permission granted
29 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
4 March 2025
Operator or applicant
Renewable Energy Systems
Planning authority
Highland
Planning application reference
23/05999/FUL
Address (REPD)
Land 410M NE Of The Smithy Alness
Council area (by location)
Highland
Time to decision
56 weeks
Name in REPD
The Smithy - Battery Storage
REPD reference
14676

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Strathrory Wind Farmwind farm36approved, not built6.6
Torr Leathann, Ardrossbattery storage5refused6.8
Torr Leathann, Ardross Wind Farmwind farm36refused6.8
Drumore Cottage, Swordalebattery storage49.9approved, not built8.5
Bendealt Wind Farm, Highlandwind farm9operational8.7
Meall an Tuirc Wind Farmwind farm17operational8.7
Novar Wind Farm (Extension)wind farm36.8operational8.7
Coire Na Cloiche Wind Farmwind farm29.9operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.7077, -4.2798).