Energy Projects Near You

Solar, wind and battery projects near Evanton (IV16)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV16 (Highland): 4 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Ceislein Wind Farm (77 MW wind farm, application submitted on 13 March 2026, no decision recorded), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
4awaiting a decision
3approved, not running
3operational

Projects within 10 km of IV16

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Drumore Cottage, Swordalebattery storagebattery storage49.9approved, not builtupdated Jan 2025Jun 2023granted Dec 2024Jan 2025Highland3.1
The Smithybattery storagebattery storage45approved, not builtupdated Mar 2025Jan 2024granted Jan 2025Mar 2025Highland5.9
Woodlands Wind Farmwind farmwind farm15application withdrawnupdated Dec 2014Dec 2013—Dec 2014Highland6.1
Bendealt Wind Farm, Highlandwind farmwind farm9operationalupdated Apr 2011May 1995granted Aug 1996Apr 2011Highland6.9
Novar Wind Farm (Extension)wind farmwind farm36.8operationalupdated Dec 2012May 2003granted Jun 2005Dec 2012Highland7.3
Meall an Tuirc Wind Farmwind farmwind farm17operationalupdated Dec 2009May 1995granted Aug 1996Dec 2009Highland7.3
Ceislein Wind Farmwind farmwind farm77application submittedupdated Apr 2026Mar 2026—Apr 2026Highland9.1
Ceislein Wind Farmbattery storagebattery storage65application submittedupdated Apr 2026Mar 2026—Apr 2026Highland9.1
Clach Liath Wind Farmwind farmwind farm42.5refusedupdated Feb 2013Apr 2012refused Feb 2013Feb 2013—9.2
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alness Academysolar farmsolar farm0.5under constructionupdated Feb 2020Jan 2019granted Mar 2019Feb 2020Highland6.1
Creachan Wind Farm & BESSwind farmwind farm—application submittedupdated Apr 2026Feb 2026—Apr 2026Highland6.4
Creachan Wind Farm & BESSbattery storagebattery storage—application submittedupdated Apr 2026Feb 2026—Apr 2026Highland6.4
Swordale Wind turbinewind turbinewind turbine0.6refusedupdated Oct 2021Mar 2021refused Sep 2021Oct 2021Highland9.4

Distance from the average position of the IV16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.5
Wind farm7203177
Wind turbine100010
Battery storage42200160

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.