Glenmorie Wind Farm (134 MW)

Glenmorie Wind Farm is a 134 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 August 2014; the record was last updated on 15 March 2016. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

134 MWwind farm
refusedstatus in REPD
15 March 2016record last updated
Highlandcouncil area

Planning timeline

DateStage
11 November 2011Application submitted
21 August 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
134 MW
Status (REPD)
refused
Record last updated
15 March 2016
Operator or applicant
Wind Energy (Glenmorie) Ltd
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
34
Address (REPD)
located on the Glencalvie and the Kildermorie Estates to the south west of Bonar Bridge, at the head of Strathcarron.
Council area (by location)
Highland
Time to decision
145 weeks
REPD reference
4372

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glen Calvie Wind Farm, Ardgaywind farm69abandoned6.8
Coire Na Cloiche Wind Farmwind farm29.9operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.7983, -4.5291).