Energy Projects Near You

Carn Gorm Wind Farm (42 MW)

Carn Gorm Wind Farm is a 42 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 9 November 2015; the record was last updated on 30 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWwind farm
refused on appealstatus in REPD
30 November 2015record last updated
Highlandcouncil area

Planning timeline

DateStage
20 December 2013Application submitted
5 September 2014Refused by the planning authority
4 December 2014Appeal lodged
9 November 2015Appeal refused

Project details

Technology
wind farm
Capacity
42 MW
Status (REPD)
refused on appeal
Record last updated
30 November 2015
Operator or applicant
P I Renewables Ltd
Planning authority
Highland
Planning application reference
13/04791/FUL
Appeal reference
PPA-270-2117
Turbines
14
Address (REPD)
Land 4KM North East Of Garve
Council area (by location)
Highland
Time to decision
37 weeks
REPD reference
4481

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Fearna Wind Farmwind farm84.6application submitted3.5
Kirkan Wind Farmwind farm81.6approved, not built4.0
Lochluichart Energy Storage Facilitybattery storage49.9approved, not built6.0
Corriemoilliewind farm54.4operational8.7
Lochluichart East, Ardachybattery storage36application submitted9.4
Clach Liath Wind Farmwind farm42.5refused9.9
Lochluichart Wind Farm Extension 2wind farm24approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6338, -4.643).