Corriemoillie (54.4 MW wind farm)

Corriemoillie is a 54.4 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 April 2017; the record was last updated on 2 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

54.4 MWwind farm
operationalstatus in REPD
2 January 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
5 October 2010Application submitted
23 March 2011Planning permission granted
15 October 2015Construction started
26 April 2017Operational

Project details

Technology
wind farm
Capacity
54.4 MW
Status (REPD)
operational
Record last updated
2 January 2020
Operator or applicant
EDF Energy Renewables
Planning authority
Highland
Planning application reference
10/04137/FUL
Turbines
17
Turbine height
125 m
Address (REPD)
Garve
Council area (by location)
Highland
Time to decision
24 weeks
REPD reference
4120

Earlier applications for this site

ApplicationMWSubmittedOutcome
Corriemoillie Forest 09/00693/FULRC47.52 December 2009withdrawn 5 October 2010

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lochluichart Wind Farm Extension 2wind farm24approved, not built2.8
Lochluichartwind farm51operational3.0
Lochluichart (Extension)wind farm18operational4.3
Lochluichart East, Ardachybattery storage36application submitted5.0
Lochluichart Energy Storage Facilitybattery storage49.9approved, not built5.9
Carn Fearna Wind Farmwind farm84.6application submitted8.0
Carn Gorm Wind Farmwind farm42refused on appeal8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6687, -4.773).