Energy Projects Near You

Solar, wind and battery projects near Strathpeffer (IV14)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV14 (Highland): 3 are waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Carn Fearna Wind Farm (84.6 MW wind farm, application submitted on 15 April 2025, no decision recorded), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
3awaiting a decision
1approved, not running
1operational

Projects within 10 km of IV14

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kirkan Wind Farmwind farmwind farm81.6approved, not built may be out of dateupdated Aug 2023Mar 2019granted Jul 2023Aug 2023—7.5
Ceislein Wind Farmwind farmwind farm77application submittedupdated Apr 2026Mar 2026—Apr 2026Highland7.6
Ceislein Wind Farmbattery storagebattery storage65application submittedupdated Apr 2026Mar 2026—Apr 2026Highland7.6
Fairburnwind farmwind farm43operationalupdated Aug 2011May 2005granted Jan 2008Aug 2011Highland7.6
Fairburn Extensionwind farmwind farm36application withdrawnupdated Feb 2014Jul 2013—Feb 2014Highland7.6
Carn Gorm Wind Farmwind farmwind farm42refused on appealupdated Nov 2015Dec 2013refused Sep 2014Nov 2015Highland7.7
Carn Fearna Wind Farmwind farmwind farm84.6application submittedupdated Jun 2025Apr 2025—Jun 2025Highland8.8
Woodlands Wind Farmwind farmwind farm15application withdrawnupdated Dec 2014Dec 2013—Dec 2014Highland9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Somerby Farm, Lochussiewind turbinewind turbine0.4refusedupdated Jul 2024Jan 2024refused May 2024Jul 2024Highland4.3
Knockbain Farmwind turbinewind turbine—refusedupdated Jun 2025Oct 2024refused May 2025Jun 2025Highland5.7
Swordale Wind turbinewind turbinewind turbine0.6refusedupdated Oct 2021Mar 2021refused Sep 2021Oct 2021Highland7.3

Distance from the average position of the IV14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm72111243
Wind turbine300030
Battery storage1100065

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV14, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.