Kirkan Wind Farm (81.6 MW)

Kirkan Wind Farm is an 81.6 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 July 2023, not yet built; the record was last updated on 10 August 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. REPD also records that the planning permission expired on 25 July 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

81.6 MWwind farm
approved, not builtmay be out of datestatus in REPD
10 August 2023record last updated
Scotlandcouncil area

REPD also records that the planning permission expired on 25 July 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
14 March 2019Application submitted
25 July 2023Section 36 consent granted (Scottish Ministers)
25 July 2026Permission expired

Project details

Technology
wind farm
Capacity
81.6 MW
Status (REPD)
approved, not built
Record last updated
10 August 2023
Operator or applicant
Coriolis Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001800
Turbines
17
Turbine height
175 m
Address (REPD)
Land 3015M SE Of Aultguish Inn, Garve,
Council area (by location)
not known
Time to decision
228 weeks
REPD reference
6634

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Gorm Wind Farmwind farm42refused on appeal4.0
Clach Liath Wind Farmwind farm42.5refused5.9
Lochluichart Energy Storage Facilitybattery storage49.9approved, not built6.8
Carn Fearna Wind Farmwind farm84.6application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.6503, -4.5829).