Energy Projects Near You

Solar, wind and battery projects near Muir of Ord (IV6)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV6 (Highland): 5 are waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Ballach Wind Farm (144 MW wind farm, application submitted on 6 August 2025, no decision recorded), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
5awaiting a decision
1approved, not running
0operational

Projects within 10 km of IV6

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dunballoch Farm, Dunballochbattery storagebattery storage100application submittedupdated May 2025Dec 2024—May 2025Highland6.3
Balblair Quarry, Balblair Battery Energy Storeage Systembattery storagebattery storage49.9approved, not builtupdated Jun 2025Apr 2024granted May 2025Jun 2025Highland6.4
Ballach Wind Farmwind farmwind farm144application submittedupdated Oct 2025Aug 2025—Oct 2025Highland6.9
Ballach Wind Farmbattery storagebattery storage5application submittedupdated Oct 2025Aug 2025—Oct 2025Highland6.9
Caulternich Croft Energy Storage Projectbattery storagebattery storage49.9refusedupdated Jul 2025Jun 2023refused Dec 2024Jul 2025Highland7.3
Ceislein Wind Farmwind farmwind farm77application submittedupdated Apr 2026Mar 2026—Apr 2026Highland8.2
Ceislein Wind Farmbattery storagebattery storage65application submittedupdated Apr 2026Mar 2026—Apr 2026Highland8.2
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Somerby Farm, Lochussiewind turbinewind turbine0.4refusedupdated Jul 2024Jan 2024refused May 2024Jul 2024Highland6.4
Knockbain Farmwind turbinewind turbine—refusedupdated Jun 2025Oct 2024refused May 2025Jun 2025Highland7.8
Swordale Wind turbinewind turbinewind turbine0.6refusedupdated Oct 2021Mar 2021refused Sep 2021Oct 2021Highland7.9

Distance from the average position of the IV6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm22000221
Wind turbine300030
Battery storage53101220

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.