Energy Projects Near You

Balblair Quarry, Balblair Battery Energy Storeage System (49.9 MW)

Balblair Quarry, Balblair Battery Energy Storeage System is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 May 2025, not yet built; the record was last updated on 18 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
18 June 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
19 April 2024Application submitted
30 May 2025Planning permission granted
30 May 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
18 June 2025
Operator or applicant
Lovat Estates Limited (LG-B-50a Limited)
Planning authority
Highland
Planning application reference
24/01548/FUL
Address (REPD)
340M SW Of Balblair Quarry Balblair Beauly
Council area (by location)
Highland
Time to decision
58 weeks
Name in REPD
Balblair Quarry, Balblair - Battery Energy Storeage System
REPD reference
14635

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dunballoch Farm, Dunballochbattery storage100application submitted1.4
Ballach Wind Farmwind farm144application submitted1.4
Caulternich Croft Energy Storage Projectbattery storage49.9refused1.9
Druim Ba Windfarmwind farm30refused on appeal6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4704, -4.484).