Fairburn (43 MW wind farm)

Fairburn is a 43 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 June 2010; the record was last updated on 8 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43 MWwind farm
operationalstatus in REPD
8 August 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
10 May 2005Application submitted
1 January 2008Planning permission granted
1 February 2009Construction started
7 June 2010Operational

Project details

Technology
wind farm
Capacity
43 MW
Status (REPD)
operational
Record last updated
8 August 2011
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Highland
Planning application reference
05/00436/FULRC
Turbines
20
Address (REPD)
Fairburn Marybank
Council area (by location)
Highland
Time to decision
138 weeks
REPD reference
4675

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fairburn Extensionwind farm36application withdrawn<0.1
Carn Fearna Wind Farmwind farm84.6application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5329, -4.6315).