Energy Projects Near You

Hill of Nigg (7.5 MW wind farm)

Hill of Nigg is a 7.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 June 2015; the record was last updated on 1 July 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
refusedstatus in REPD
1 July 2015record last updated
Highlandcouncil area

Planning timeline

DateStage
13 January 2015Application submitted
5 June 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
refused
Record last updated
1 July 2015
Operator or applicant
West Coast Energy
Planning authority
Highland
Planning application reference
15/00093/FUL
Turbines
3
Turbine height
115 m
Address (REPD)
Land South of Wester Rarichie Darm, Fearn
Council area (by location)
Highland
Time to decision
20 weeks
REPD reference
3635

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nigg Hillwind farm10refused0.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.7275, -3.9541).