Energy Projects Near You

Solar, wind and battery projects near Dunbeath (KW6)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW6 (Highland): 2 are waiting for a planning decision, 2 operational. The largest live scheme is Hill Of Lynchrobbie, Dunbeath (7.2 MW wind farm, application submitted on 3 February 2025, no decision recorded), 4.7 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Moray West Offshore Wind Farm Project (882 MW, operational), 21.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
2awaiting a decision
0approved, not running
2operational

Projects within 10 km of KW6

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hill Of Lychrobbiewind farmwind farm2.4permission expiredupdated Jun 2020Nov 2013granted Jan 2017Jun 2020Highland2.6
Hill Of Lynchrobbie, Dunbeathbattery storagebattery storage5application submittedupdated Feb 2025Feb 2025—Feb 2025Highland2.9
Dunbeathwind farmwind farm66refusedupdated Jun 2013Aug 2005refused Jun 2013Jun 2013Highland3.9
Upper Smerral Wind Clusterwind farmwind farm2.7refusedupdated Sep 2014Sep 2013refused May 2014Sep 2014Highland4.3
Hill Of Lynchrobbie, Dunbeathwind farmwind farm7.2application submittedupdated Feb 2025Feb 2025—Feb 2025Highland4.7
Boulfruichwind farmwind farm13operationalupdated Oct 2009Sep 2001granted May 2002Oct 2009Highland5.5
Forse Wind Farmwind farmwind farm60abandonedupdated Sep 2018——Sep 2018Highland8.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lower Rumster wind turbinewind farmwind farm0.2operationalupdated May 2022Jul 2020granted Oct 2020May 2022Highland9.0

Distance from the average position of the KW6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm710227.2
Battery storage110005

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Moray West Offshore Wind Farm Project882operationalupdated May 202621.5
Beatrice Demonstrator10operationalupdated May 201732.5
Beatrice588operationalupdated May 201934.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.