Energy Projects Near You

Beatrice Demonstrator offshore wind farm

Beatrice Demonstrator is a 10 MW offshore wind farm with 2 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 July 2007; the record was last updated on 31 May 2017. Its REPD grid reference is 19 km from the nearest postcode on land (KW2 6AB, Highland). As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWoffshore wind farm
operationalstatus in REPD
31 May 2017record last updated
19 km from land (Highland)REPD location

Consent timeline

DateStage
23 January 2006Application submitted
15 June 2006Section 36 consent granted (Scottish Ministers)
1 September 2006Construction started
17 July 2007Operational

Project details

Technology
offshore wind farm
Capacity
10 MW
Turbines
2
Turbine capacity
5 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Talisman Energy
Consenting authority (REPD)
Scottish Government (S36)
Application reference
not recorded
Nearest postcode on land
KW2 6AB (Highland), 19.2 km from the REPD grid reference
Time to decision
20 weeks
REPD reference
2485

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Postcode districts within 40 km

Districtkm
Whaligoe (KW2)19.3
Lybster (KW3)23.7
Wick (KW1)26.5
Latheronwheel (KW5)29.1
Dunbeath (KW6)32.5
Berriedale (KW7)36.7

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Beatrice588operational18.7

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (58.2528, -2.8884).