Energy Projects Near You

Solar, wind and battery projects near Wick (KW1)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW1 (Highland): 1 approved but not yet running, 6 operational. The largest live scheme is Wick Airport Industrial Estate (0.3 MW rooftop solar, approved on 22 June 2022, not yet built; REPD status may be out of date), 2.0 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Beatrice Demonstrator (10 MW, operational), 26.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
1approved, not running
6operational

Projects within 10 km of KW1

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Causeymirewind farmwind farm48.3operationalupdated May 2017Nov 2001granted Nov 2002May 2017Highland2.6
Achairnwind farmwind farm6.2operationalupdated Jun 2010Aug 2004granted Mar 2006Jun 2010Highland5.1
Wathegar 2 Wind Farmwind farmwind farm18.5operationalupdated Jan 2020Oct 2011granted Mar 2012Jan 2020Highland6.0
Wathegar wind farmwind farmwind farm10operationalupdated Jun 2013Feb 2010granted May 2010Jun 2013Highland6.3
Camster IIwind farmwind farm36operationalupdated May 2026Aug 2019granted Jul 2021May 2026Highland7.2
Bilbster Wind Farmwind farmwind farm3.9operationalupdated Oct 2009Jan 2004—Oct 2009Highland7.5
Cogle Moss Wind Farmwind farmwind farm36permission expiredupdated Jan 2020Aug 2015granted Aug 2017Jan 2020Highland7.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wick Airport Industrial Estaterooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Mar 2022granted Jun 2022Apr 2022Highland2.0

Distance from the average position of the KW1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.3
Wind farm700600

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Beatrice Demonstrator10operationalupdated May 201726.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KW1, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.