Energy Projects Near You

Causeymire (48.3 MW wind farm)

Causeymire is a 48.3 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2004; the record was last updated on 18 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48.3 MWwind farm
operationalstatus in REPD
18 May 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
1 November 2001Application submitted
19 November 2002Planning permission granted
1 June 2004Operational

Project details

Technology
wind farm
Capacity
48.3 MW
Status (REPD)
operational
Record last updated
18 May 2017
Operator or applicant
Innogy (formerly RWE npower)
Planning authority
Highland
Planning application reference
01/00361/FULCA
Turbines
24
Address (REPD)
Causey Mire, Caithness, Highlands
Council area (by location)
Highland
Time to decision
55 weeks
REPD reference
3108

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Achairnwind farm6.2operational6.8
Wathegar 2 Wind Farmwind farm18.5operational7.6
Wathegar wind farmwind farm10operational8.2
Camster IIwind farm36operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4435, -3.0854).