Energy Projects Near You

Wathegar 2 Wind Farm (18.5 MW)

Wathegar 2 Wind Farm is an 18.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 September 2017; the record was last updated on 2 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.5 MWwind farm
operationalstatus in REPD
2 January 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
10 October 2011Application submitted
23 March 2012Planning permission granted
13 December 2016Construction started
15 September 2017Operational

Project details

Technology
wind farm
Capacity
18.5 MW
Status (REPD)
operational
Record last updated
2 January 2020
Operator or applicant
BayWa r.e.
Planning authority
Highland
Planning application reference
11/03671/FUL
Turbines
9
Address (REPD)
Wathegar, Bilbster, Wick
Council area (by location)
Highland
Time to decision
24 weeks
REPD reference
4425

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wathegar wind farmwind farm10operational0.7
Achairnwind farm6.2operational0.9
Camster IIwind farm36operational2.0
Camsterwind farm50operational4.4
Cogle Moss Wind Farmwind farm36permission expired5.9
Watten Wind Farmwind farm47.6application withdrawn6.4
Cnoc Morailwind farm11.5refused7.3
Causeymirewind farm48.3operational7.6
Burn of Whilkwind farm22.5operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4352, -3.2159).