Camster II (36 MW wind farm)

Camster II is a 36 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2026; the record was last updated on 14 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
operationalstatus in REPD
14 May 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
7 August 2019Application submitted
12 January 2021Refused by the planning authority
28 July 2021Planning permission granted
28 July 2021Appeal allowed
1 October 2023Construction started
1 April 2026Operational

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
operational
Record last updated
14 May 2026
Operator or applicant
E.ON UK
Planning authority
Highland
Planning application reference
19/03015/FUL
Appeal reference
PPA-270-2242
Turbines
10
Turbine height
127 m
Address (REPD)
Watten and Lybster
Council area (by location)
Highland
Time to decision
103 weeks
Contracts for Difference
AR5
REPD reference
4351

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wathegar 2 Wind Farmwind farm18.5operational2.0
Wathegar wind farmwind farm10operational2.4
Achairnwind farm6.2operational2.6
Camsterwind farm50operational3.1
Burn of Whilkwind farm22.5operational6.9
Watten Wind Farmwind farm47.6application withdrawn7.6
Cogle Moss Wind Farmwind farm36permission expired7.7
Cnoc Morailwind farm11.5refused7.9
Causeymirewind farm48.3operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4178, -3.2206).