Energy Projects Near You

Burn of Whilk (22.5 MW wind farm)

Burn of Whilk is a 22.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 August 2015; the record was last updated on 3 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
operationalstatus in REPD
3 November 2015record last updated
Highlandcouncil area

Planning timeline

DateStage
23 February 2007Application submitted
30 March 2011Planning permission granted
30 May 2014Construction started
7 August 2015Operational

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
operational
Record last updated
3 November 2015
Operator or applicant
RWE npower
Planning authority
Highland
Planning application reference
06/00676/FULCA.
Turbines
9
Address (REPD)
Burn of Whilk Hill of Yarrows Caithness
Council area (by location)
Highland
Time to decision
214 weeks
REPD reference
4122

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Camster IIwind farm36operational6.9
Camsterwind farm50operational7.0
Golticlay Wind Farm 2wind farm13.2no application required7.4
Golticlay Wind Farmwind farm72.6under construction7.4
Wathegar 2 Wind Farmwind farm18.5operational8.7
Achairnwind farm6.2operational9.1
Wathegar wind farmwind farm10operational9.3
Forse Wind Farmwind farm60abandoned10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.3568, -3.2039).