Energy Projects Near You

Wathegar wind farm (10 MW)

Wathegar wind farm is a 10 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 4 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
4 June 2013record last updated
Highlandcouncil area

Planning timeline

DateStage
9 February 2010Application submitted
21 May 2010Planning permission granted
1 June 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
4 June 2013
Operator or applicant
Private Developer
Planning authority
Highland
Planning application reference
10/00042/FULCA
Turbines
5
Address (REPD)
Land At Wathegar Bilbster, Wick, Caithness
Council area (by location)
Highland
Time to decision
14 weeks
REPD reference
3757

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wathegar 2 Wind Farmwind farm18.5operational0.7
Achairnwind farm6.2operational1.4
Camster IIwind farm36operational2.4
Camsterwind farm50operational4.3
Cogle Moss Wind Farmwind farm36permission expired5.3
Watten Wind Farmwind farm47.6application withdrawn5.7
Cnoc Morailwind farm11.5refused6.6
Causeymirewind farm48.3operational8.2
Burn of Whilkwind farm22.5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4393, -3.2257).