Watten Wind Farm (47.6 MW)

Watten Wind Farm is a 47.6 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 22 January 2026; the record was last updated on 22 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47.6 MWwind farm
application withdrawnstatus in REPD
22 June 2026record last updated
Highlandcouncil area

Planning timeline

DateStage
14 August 2023Application submitted
22 January 2026Application withdrawn

Project details

Technology
wind farm
Capacity
47.6 MW
Status (REPD)
application withdrawn
Record last updated
22 June 2026
Operator or applicant
EDF Energy Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004509
Turbines
7
Turbine height
220 m
Address (REPD)
Sw/O Watten, Caithness
Council area (by location)
Highland
REPD reference
11479

The scheme also includes 20 MW of battery storage, recorded separately in REPD (application withdrawn).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cnoc Morailwind farm11.5refused2.2
Cogle Moss Wind Farmwind farm36permission expired3.8
Wathegar wind farmwind farm10operational5.7
Spittal Hillwind farm21refused on appeal6.4
Wathegar 2 Wind Farmwind farm18.5operational6.4
Achairnwind farm6.2operational6.9
Camsterwind farm50operational7.1
Spittal Mains, Spittalbattery storage300application submitted7.2
Spittal Mains Quarrybattery storage49.9approved, not built7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4706, -3.3035).