Cnoc Morail (11.5 MW wind farm)

Cnoc Morail is an 11.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 19 January 2016; the record was last updated on 23 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWwind farm
refusedstatus in REPD
23 December 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
21 November 2014Application submitted
19 January 2016Refused by the planning authority

Project details

Technology
wind farm
Capacity
11.5 MW
Status (REPD)
refused
Record last updated
23 December 2014
Operator or applicant
Wpd Scotland Limited
Planning authority
Highland
Planning application reference
14/04375/FUL
Turbines
5
Turbine height
100 m
Address (REPD)
Land 1200M NW Of Acharole 18 West Watten Watten
Council area (by location)
Highland
Time to decision
61 weeks
REPD reference
3345

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Watten Wind Farmwind farm47.6application withdrawn2.2
Spittal Hillwind farm21refused on appeal5.4
Spittal Mains, Spittalbattery storage300application submitted5.5
Spittal Mains Quarrybattery storage49.9approved, not built5.5
Cogle Moss Wind Farmwind farm36permission expired6.0
Camsterwind farm50operational6.5
Wathegar wind farmwind farm10operational6.6
Mybster Farm, Wattenbattery storage19.8application withdrawn6.6
Bad a Cheo Wind Farmwind farm26.7operational7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4579, -3.3333).