Solar, wind and battery projects near Halkirk (KW12)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW12 (Highland): 6 are waiting for a planning decision, 8 approved but not yet running, 2 operational. The largest live scheme is Spittal Mains, Spittal (300 MW battery storage, application submitted on 19 December 2024, no decision recorded), 6.0 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Dounreay Trì Floating Wind Demonstration (10 MW, under construction), 30.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KW12
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Achiesbattery storage | battery storage | 162 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | Highland | 4.1 |
| Wind Farm at Achlachan Windfarmwind farm | wind farm | 8.5 | approved, not builtupdated Nov 2025 | Apr 2025 | granted Oct 2025 | Nov 2025 | Highland | 4.1 |
| Buckies Hill Wind Farmwind farm | wind farm | 4.5 | refusedupdated May 2015 | Nov 2014 | refused Apr 2015 | May 2015 | Highland | 4.4 |
| Spittal Hillwind farm | wind farm | 21 | refused on appealupdated May 2015 | Dec 2013 | refused Sep 2014 | May 2015 | Highland | 5.4 |
| Hill of Lieurarywind farm | wind farm | 8 | refusedupdated May 2006 | Jul 2003 | refused Sep 2005 | May 2006 | Highland | 5.5 |
| Spittal Mains, Spittalbattery storage | battery storage | 300 | application submittedupdated Apr 2025 | Dec 2024 | — | Apr 2025 | Highland | 6.0 |
| Spittal Mains Quarrybattery storage | battery storage | 49.9 | approved, not builtupdated May 2025 | Jul 2024 | granted Mar 2025 | May 2025 | Highland | 6.0 |
| Mybster Farm, Wattenbattery storage | battery storage | 19.8 | application withdrawn | Apr 2026 | — | — | Highland | 6.4 |
| Achlachan Wind Farmwind farm | wind farm | 10 | operationalupdated Jun 2019 | Apr 2013 | granted Nov 2013 | Jun 2019 | Highland | 6.8 |
| Buckies Farmbattery storage | battery storage | 49.9 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Highland | 6.8 |
| Geiselittle Farmbattery storage | battery storage | 49.9 | approved, not builtupdated Nov 2025 | Aug 2024 | granted Aug 2025 | Nov 2025 | Highland | 7.0 |
| Stainland Energy Storage Projectbattery storage | battery storage | 49.9 | approved, not builtupdated Jan 2025 | May 2022 | granted Nov 2022 | Jan 2025 | Highland | 7.3 |
| Achlachan Wind Farm - Phase 2wind farm | wind farm | 6.9 | abandonedupdated Jun 2019 | May 2015 | granted Mar 2016 | Jun 2019 | Highland | 7.6 |
| Durran Mainswind farm | wind farm | 19.5 | refusedupdated Sep 2011 | Aug 2008 | refused Nov 2010 | Sep 2011 | Highland | 8.0 |
| Oak Tree Cottage, Castletownwind turbine | wind turbine | 4.3 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Highland | 8.2 |
| Castletown Wind Farmwind farm | wind farm | 9.6 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | Highland | 8.7 |
| Castletown Wind Farmbattery storage | battery storage | 12 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | Highland | 8.9 |
| Halsary Wind Farmwind farm | wind farm | 34 | operationalupdated Apr 2021 | Nov 2009 | granted Sep 2013 | Apr 2021 | Highland | 8.9 |
| Hoy Farmwind turbine | wind turbine | 2.3 | refusedupdated Oct 2017 | Oct 2016 | refused Sep 2017 | Oct 2017 | Highland | 9.3 |
| Kirkton Energy Farmwind farm | wind farm | 52.8 | refusedupdated May 2026 | Nov 2022 | refused Jan 2026 | May 2026 | Highland | 9.9 |
| Kirkton Energy Farmbattery storage | battery storage | 20 | refusedupdated May 2026 | Nov 2022 | refused Jan 2026 | May 2026 | Highland | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Loch Calder Water Treatment Workrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2025 | Aug 2025 | granted Sep 2025 | Oct 2025 | Highland | 1.6 |
| Quarry Braerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Oct 2025 | Dec 2025 | Highland | 1.7 |
| Loch Calder Water Treatment Works, Quarry Braesolar farm | solar farm | 0.3 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Highland | 1.7 |
| Mybster Croft, Spittalbattery storage | battery storage | — | approved, not builtupdated May 2025 | Nov 2023 | granted Mar 2025 | May 2025 | Highland | 6.7 |
Distance from the average position of the KW12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.3 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 1.3 |
| Wind farm | 10 | 1 | 1 | 2 | 5 | 18.1 |
| Wind turbine | 2 | 1 | 0 | 0 | 1 | 4.3 |
| Battery storage | 10 | 4 | 4 | 0 | 1 | 674 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Dounreay Trì Floating Wind Demonstration | 10 | under constructionupdated Dec 2019 | 30.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Highland decides solar, wind and battery applications
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.