Geiselittle Farm (49.9 MW battery storage)

Geiselittle Farm is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 August 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
7 November 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
23 August 2024Application submitted
20 August 2025Planning permission granted
20 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Whirlwind Renewables
Planning authority
Highland
Planning application reference
24/03500/FUL
Address (REPD)
530m S/O Geiselittle Farm
Council area (by location)
Highland
Time to decision
52 weeks
Name in REPD
Geiselittle Farm - Battery Energy Storage
REPD reference
15387

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stainland Energy Storage Projectbattery storage49.9approved, not built0.4
Buckies Farmbattery storage49.9application submitted1.7
Kirkton Energy Farmwind farm52.8refused3.6
Hill of Lieurarywind farm8refused5.7
Durran Mainswind farm19.5refused7.3
Cairnmore Hill Wind Farmwind farm21refused7.9
Castletown Wind Farmwind farm9.6application submitted9.0
Baillie Wind Farmwind farm52.5operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5694, -3.5062).