Stainland Energy Storage Project (49.9 MW)

Stainland Energy Storage Project is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 November 2022, not yet built; the record was last updated on 14 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
14 January 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
23 May 2022Application submitted
4 November 2022Planning permission granted
4 November 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
14 January 2025
Operator or applicant
Whirlwind Energy Storage Limited
Planning authority
Highland
Planning application reference
22/02054/FUL
Address (REPD)
E/O The A9 N/O Upper Geiselittle Thurso
Council area (by location)
Highland
Time to decision
24 weeks
REPD reference
10225

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Geiselittle Farmbattery storage49.9approved, not built0.4
Buckies Farmbattery storage49.9application submitted2.0
Kirkton Energy Farmwind farm52.8refused3.6
Hill of Lieurarywind farm8refused6.0
Durran Mainswind farm19.5refused7.2
Cairnmore Hill Wind Farmwind farm21refused7.9
Castletown Wind Farmwind farm9.6application submitted8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5722, -3.503).