Energy Projects Near You

Solar, wind and battery projects near Thurso (KW14)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW14 (Highland): 2 are waiting for a planning decision, 7 approved but not yet running, 5 operational. The largest live scheme is Buckies Farm (49.9 MW battery storage, application submitted on 5 February 2026, no decision recorded), 3.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Dounreay Trì Floating Wind Demonstration (10 MW, under construction), 22.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
2awaiting a decision
7approved, not running
5operational

Projects within 10 km of KW14

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kirkton Energy Farmwind farmwind farm52.8refusedupdated May 2026Nov 2022refused Jan 2026May 2026Highland0.1
Kirkton Energy Farmbattery storagebattery storage20refusedupdated May 2026Nov 2022refused Jan 2026May 2026Highland0.1
Buckies Farmbattery storagebattery storage49.9application submittedupdated Mar 2026Feb 2026—Mar 2026Highland3.0
Stainland Energy Storage Projectbattery storagebattery storage49.9approved, not builtupdated Jan 2025May 2022granted Nov 2022Jan 2025Highland3.5
Geiselittle Farmbattery storagebattery storage49.9approved, not builtupdated Nov 2025Aug 2024granted Aug 2025Nov 2025Highland3.5
Cairnmore Hill Wind Farmwind farmwind farm21refusedupdated Mar 2025Sep 2022refused Feb 2025Mar 2025Highland4.5
Buckies Hill Wind Farmwind farmwind farm4.5refusedupdated May 2015Nov 2014refused Apr 2015May 2015Highland5.5
Hill of Lieurarywind farmwind farm8refusedupdated May 2006Jul 2003refused Sep 2005May 2006Highland6.4
Hill of Lybster (Wind Turbine - Extension)wind turbinewind turbine1.5operationalupdated Oct 2018Oct 2017granted Aug 2018Oct 2018Highland7.4
Baillie Wind Farmwind farmwind farm52.5operationalupdated May 2013Jul 2004granted Jan 2010May 2013Highland7.5
Forss Wind Farmwind farmwind farm4.5application submitted may be out of dateupdated Jan 2022Nov 2020—Jan 2022Highland7.6
Forss Extension (Forss III)wind farmwind farm6.5refused on appealupdated Jan 2013Oct 2010refused Oct 2011Jan 2013Highland7.8
Lythmore House, Technology Park Forssbattery storagebattery storage49.9approved, not builtupdated Sep 2025Nov 2024granted Aug 2025Sep 2025Highland7.8
Hillcrest Cottage, Shebsterbattery storagebattery storage19.9approved, not built may be out of dateupdated Sep 2022Dec 2021granted Aug 2022Sep 2022Highland7.8
Forss Wind Farm (Extension)wind farmwind farm5.2operationalupdated May 2016Jan 2005granted Oct 2006May 2016Highland7.9
Hill of Lybsterwind farmwind farm4.9operationalupdated Jun 2010Apr 2000granted Jun 2001Jun 2010Highland7.9
Forss Wind Farmwind farmwind farm2.6operationalupdated Jun 2018Jan 2001—Jun 2018Highland7.9
South Shebsterwind farmwind farm10refusedupdated Mar 2009Dec 2005refused Jan 2009Mar 2009Highland9.4
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Quarry Braerooftop solarrooftop solar0.7approved, not builtupdated Dec 2025Aug 2025granted Oct 2025Dec 2025Highland8.1
Loch Calder Water Treatment Works, Quarry Braesolar farmsolar farm0.3approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Highland8.1
Loch Calder Water Treatment Workrooftop solarrooftop solar0.7approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Highland8.7

Distance from the average position of the KW14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.3
Rooftop solar202001.3
Wind farm1110464.5
Wind turbine100100
Battery storage61401220

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Dounreay Trì Floating Wind Demonstration10under constructionupdated Dec 201922.3
West of Orkney Wind Farm2,000approved, not builtupdated Jul 202536.9

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KW14, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.