Forss Extension (Forss III) (6.5 MW wind farm)

Forss Extension (Forss III) is a 6.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 July 2012; the record was last updated on 2 January 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWwind farm
refused on appealstatus in REPD
2 January 2013record last updated
Highlandcouncil area

Planning timeline

DateStage
28 October 2010Application submitted
19 October 2011Refused by the planning authority
19 July 2012Appeal refused

Project details

Technology
wind farm
Capacity
6.5 MW
Status (REPD)
refused on appeal
Record last updated
2 January 2013
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Highland
Planning application reference
10/04434/FUL
Appeal reference
12/00002/RBREF
Turbines
5
Address (REPD)
Thurso, Caithness
Council area (by location)
Highland
Time to decision
51 weeks
REPD reference
3783

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lythmore House, Technology Park Forssbattery storage49.9approved, not built0.1
Forss Wind Farm (Extension)wind farm5.2operational0.3
Cairnmore Hill Wind Farmwind farm21refused3.3
Baillie Wind Farmwind farm52.5operational4.1
Hillcrest Cottage, Shebsterbattery storage19.9approved, not built4.6
Dounreay Windfarmwind farm17.5refused on appeal4.8
Dounreay, Thursobattery storage34under construction5.5
Titan Battery Storagebattery storage500application submitted6.0
Limekiln, Borlum Housebattery storage70application submitted6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.6042, -3.6852).