Energy Projects Near You

Lythmore House, Technology Park Forss (49.9 MW battery storage)

Lythmore House, Technology Park Forss is a 49.9 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 August 2025, not yet built; the record was last updated on 10 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
10 September 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
13 November 2024Application submitted
13 August 2025Planning permission granted
13 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 September 2025
Operator or applicant
Forss Energy Storage Limited
Planning authority
Highland
Planning application reference
24/04585/FUL
Address (REPD)
190m W/O Lythmore House, South Wing 21 Forss Business & Technology Park Forss, Forss, Thurso
Council area (by location)
Highland
Time to decision
39 weeks
Name in REPD
Lythmore House, Technology Park Forss - Battery Energy Storage
REPD reference
17703

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Forss Extension (Forss III)wind farm6.5refused on appeal0.1
Forss Wind Farm (Extension)wind farm5.2operational0.3
Cairnmore Hill Wind Farmwind farm21refused3.3
Baillie Wind Farmwind farm52.5operational4.2
Hillcrest Cottage, Shebsterbattery storage19.9approved, not built4.7
Dounreay Windfarmwind farm17.5refused on appeal4.8
Dounreay, Thursobattery storage34under construction5.6
Titan Battery Storagebattery storage500application submitted6.1
Limekiln, Borlum Housebattery storage70application submitted7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.6052, -3.6857).