Baillie Wind Farm (52.5 MW)

Baillie Wind Farm is a 52.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2013; the record was last updated on 2 May 2013. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

52.5 MWwind farm
operationalstatus in REPD
2 May 2013record last updated
Highlandcouncil area

Planning timeline

DateStage
13 July 2004Application submitted
12 January 2010Section 36 consent granted (Scottish Ministers)
1 July 2011Construction started
29 March 2013Operational

Project details

Technology
wind farm
Capacity
52.5 MW
Status (REPD)
operational
Record last updated
2 May 2013
Operator or applicant
Baillie Windfarm Ltd
Planning authority
Scottish Government (S36)
Planning application reference
04/00342/S36CA
Turbines
21
Address (REPD)
Bardnaheigh, Westfield, Thurso
Council area (by location)
Highland
Time to decision
287 weeks
REPD reference
4021

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hillcrest Cottage, Shebsterbattery storage19.9approved, not built0.6
South Shebsterwind farm10refused3.0
Forss Wind Farm (Extension)wind farm5.2operational3.9
Dounreay Windfarmwind farm17.5refused on appeal3.9
Titan Battery Storagebattery storage500application submitted4.0
Forss Extension (Forss III)wind farm6.5refused on appeal4.1
Lythmore House, Technology Park Forssbattery storage49.9approved, not built4.2
Dounreay, Thursobattery storage34under construction4.3
Cairnmore Hill Wind Farmwind farm21refused4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5679, -3.677).