Energy Projects Near You

Dounreay Trì floating offshore wind farm

Dounreay Trì Floating Wind Demonstration is a 10 MW floating offshore wind farm with 2 turbines in Scottish waters. Its status: not going ahead: the consent holder, Highland Wind Limited, states that the offshore part of the Dounreay Trì consent is no longer being implemented; the site is used for the Pentland Floating Offshore Wind Farm instead (Highland Wind Limited). The Renewable Energy Planning Database (July 2026 extract) still records: under construction since 31 March 2017; the record was last updated on 6 December 2019. Its REPD grid reference is 15 km from the nearest postcode on land (KW14 7YN, Highland). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWfloating offshore wind farm
not going aheadstatus (Highland Wind Limited; status in REPD: under construction)
6 December 2019record last updated
15 km from land (Highland)REPD location

Consent timeline

DateStage
17 October 2016Application submitted
16 March 2017Marine licence and Section 36 consent granted (Scottish Ministers)
31 March 2017Construction started
6 July 2022Offshore part of the consent no longer being implemented (Highland Wind Limited, consent holder)

Status source: Highland Wind Limited. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “under construction”.

Project details

Technology
floating offshore wind farm
Capacity
10 MW
Turbines
2
Turbine capacity
5 MW
Turbine height
201 m
Status
not going ahead (Highland Wind Limited; REPD: under construction)
Record last updated
6 December 2019
Operator or applicant
Hexicon AB/ Dounreay Tri
Consenting authority (REPD)
Marine Scotland
Application reference
16/04775/S36
Nearest postcode on land
KW14 7YN (Highland), 14.6 km from the REPD grid reference
Time to decision
21 weeks
REPD reference
6264

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Thurso (KW14)22.3
Highland (KW13)24.5
Halkirk (KW12)30.8

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
West of Orkney Wind Farm2,000approved, not built18.4
Pentland Floating Offshore Wind Farm100approved, not built23.4

All offshore wind farms in UK waters

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (58.6984, -3.8768).