Pentland floating offshore wind farm

Pentland Floating Offshore Wind Farm is a 100 MW floating offshore wind farm in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 June 2023, not yet built; the record was last updated on 19 January 2026. REPD gives a grid reference on the coast (KW14 8BH, Highland), not the position of the turbines, so the distance out to sea is not known from REPD. As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWfloating offshore wind farm
approved, not builtstatus in REPD
19 January 2026record last updated
on the coast (Highland)REPD location

Consent timeline

DateStage
9 August 2022Application submitted
28 June 2023Marine licence and Section 36 consent granted (Scottish Ministers)

Project details

Technology
floating offshore wind farm
Capacity
100 MW
Turbine height
300 m
Status (REPD)
approved, not built
Record last updated
19 January 2026
Operator or applicant
Highland Wind Limited / Copenhagen Infrastructure Partners / Eurus Energy
Consenting authority (REPD)
Marine Scotland
Application reference
not recorded
Nearest postcode on land
KW14 8BH (Highland), 0.1 km from the REPD grid reference
Time to decision
46 weeks
Contracts for Difference
AR7
REPD reference
11989

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Dounreay Trì Floating Wind Demonstration10under construction23.4

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (58.5965, -3.5238), which is on the coast rather than at the turbines.