Energy Projects Near You

Solar, wind and battery projects near Lybster (KW3)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KW3 (Highland): 4 are waiting for a planning decision, 2 approved but not yet running, 3 operational. The largest live scheme is Golticlay Wind Farm (72.6 MW wind farm, under construction since 1 July 2025), 5.3 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Beatrice Demonstrator (10 MW, operational), 23.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
4awaiting a decision
2approved, not running
3operational

Projects within 10 km of KW3

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Forse Wind Farmwind farmwind farm60abandonedupdated Sep 2018——Sep 2018Highland3.1
Golticlay Wind Farmwind farmwind farm72.6under constructionupdated Feb 2026Oct 2016granted Mar 2021Feb 2026Highland5.3
Golticlay Wind Farm 2wind farmwind farm13.2no application requiredupdated Feb 2026——Feb 2026Highland5.3
Rumster Forest Community Wind Farmwind farmwind farm2.7abandonedupdated Aug 2016Dec 2011granted Aug 2015Aug 2016Highland6.4
Burn of Whilkwind farmwind farm22.5operationalupdated Nov 2015Feb 2007granted Mar 2011Nov 2015Highland7.2
Hill Of Lynchrobbie, Dunbeathwind farmwind farm7.2application submittedupdated Feb 2025Feb 2025—Feb 2025Highland7.8
Hill Of Lynchrobbie, Dunbeathbattery storagebattery storage5application submittedupdated Feb 2025Feb 2025—Feb 2025Highland8.7
Upper Smerral Wind Clusterwind farmwind farm2.7refusedupdated Sep 2014Sep 2013refused May 2014Sep 2014Highland8.9
Hill Of Lychrobbiewind farmwind farm2.4permission expiredupdated Jun 2020Nov 2013granted Jan 2017Jun 2020Highland9.0
Boulfruichwind farmwind farm13operationalupdated Oct 2009Sep 2001granted May 2002Oct 2009Highland9.5
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Clyth Farm, Occumsterwind turbinewind turbine0.2approved, not builtupdated Oct 2023May 2023granted Oct 2023Oct 2023Highland1.9
Wind Farm at 2040m Ne/O Bulreanrobwind farmwind farm—application submittedupdated Jan 2026Dec 2025—Jan 2026Highland2.2
Golticlay Wind Farm, Bulreanrobbattery storagebattery storage—application submittedupdated Jan 2026Dec 2025—Jan 2026Highland2.4
Lower Rumster wind turbinewind farmwind farm0.2operationalupdated May 2022Jul 2020granted Oct 2020May 2022Highland3.3

Distance from the average position of the KW3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm11213179.8
Wind turbine101000.2
Battery storage220005

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Beatrice Demonstrator10operationalupdated May 201723.7
Moray West Offshore Wind Farm Project882operationalupdated May 202626.4
Beatrice588operationalupdated May 201931.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.