North-east of Bulreanrob near Lybster, RWE Renewables UK Limited is building an onshore wind farm: 11 turbines, each 180 m tall, 72.6 MW. It has been listed as under construction since 1 July 2025, more than four years after the consent. The project received a Contract for Difference in round AR6.
Why the consent took 230 weeks
The application was submitted on 28 October 2016, and an appeal was lodged on 30 October 2017. It was allowed on 24 March 2021, and on the same day Scottish Ministers granted Section 36 consent. That is almost twice their median of 127 weeks; 18% of applications are refused.
Neighbours within 10 km
Camster at 50 MW and Burn of Whilk at 22.5 MW are operational, while Forse at 60 MW has been abandoned. A separate record, Golticlay Wind Farm 2 at 13.2 MW, is listed at the same spot. For everything else nearby, see the pages for KW3 and Highland. Record last updated 23 February 2026; stages taken from the REPD extract for July 2026.