Energy Projects Near You

Beatrice offshore wind farm

Beatrice is a 588 MW offshore wind farm with 84 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 August 2019; the record was last updated on 31 May 2019. Its REPD grid reference is 30 km from the nearest postcode on land (KW3 6AX, Highland). As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

588 MWoffshore wind farm
operationalstatus in REPD
31 May 2019record last updated
30 km from land (Highland)REPD location

Consent timeline

DateStage
25 April 2012Application submitted
19 March 2014Section 36 consent granted (Scottish Ministers)
2 April 2017Construction started
5 August 2019Operational

Project details

Technology
offshore wind farm
Capacity
588 MW
Turbines
84
Turbine capacity
7 MW
Status (REPD)
operational
Record last updated
31 May 2019
Operator or applicant
Scottish & Southern Energy (SSE) / Repsol / CIP
Consenting authority (REPD)
Scottish Government (S36)
Application reference
not recorded
Nearest postcode on land
KW3 6AX (Highland), 29.8 km from the REPD grid reference
Time to decision
99 weeks
Contracts for Difference
AR1
REPD reference
2521

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Postcode districts within 40 km

Districtkm
Lybster (KW3)31.0
Whaligoe (KW2)31.5
Latheronwheel (KW5)33.6
Dunbeath (KW6)34.1
Berriedale (KW7)34.2

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Moray East950operational16.4
Beatrice Demonstrator10operational18.7
Moray West Offshore Wind Farm Project882operational21.4

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (58.0882, -2.9502).

Beatrice stands in the open sea roughly 30 km off the Highland coast; the nearest postcode districts are KW3 (Lybster) and KW2. The site holds 84 turbines of 7 MW each, 588 MW in total. According to the REPD extract from July 2026, it is the tenth-largest of the operational offshore wind farms by capacity.

From application to grid

The application was submitted on 25 April 2012; the register lists SSE, Repsol and CIP as the operators. Scottish Ministers granted Section 36 consent on 19 March 2014, after 99 weeks against their median of 81.1 for offshore wind. The Contract for Difference came in the AR1 round, construction began on 2 April 2017, and the farm became operational on 5 August 2019.

Neighbours in the same patch of sea

Beatrice Demonstrator, at 10 MW, is recorded as a separate, earlier project. Both Moray farms are bigger: Moray East at 950 MW and Moray West at 882 MW. The Beatrice record was last updated on 31 May 2019 and has not been updated since, so later events are missing from it.