Hill of Lieurary (8 MW wind farm)

Hill of Lieurary is an 8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 September 2005; the record was last updated on 9 May 2006.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
refusedstatus in REPD
9 May 2006record last updated
Highlandcouncil area

Planning timeline

DateStage
10 July 2003Application submitted
16 September 2005Refused by the planning authority

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
refused
Record last updated
9 May 2006
Operator or applicant
Scotrenewables
Planning authority
Highland
Planning application reference
CA2003323
Appeal reference
P/PPA/270/369
Turbines
3
Address (REPD)
Hill of Lieurary Westfield Thurso Caithness
Council area (by location)
Highland
Time to decision
114 weeks
REPD reference
3182

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Buckies Farmbattery storage49.9application submitted4.2
Geiselittle Farmbattery storage49.9approved, not built5.7
Stainland Energy Storage Projectbattery storage49.9approved, not built6.0
Kirkton Energy Farmwind farm52.8refused6.4
South Shebsterwind farm10refused6.8
Hillcrest Cottage, Shebsterbattery storage19.9approved, not built7.1
Broubster Forestwind farm116application withdrawn7.2
Baillie Wind Farmwind farm52.5operational7.2
Limekiln Wind Farm (Extension) Batterybattery storage5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.532, -3.5731).