Durran Mains (19.5 MW wind farm)

Durran Mains is a 19.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 November 2010; the record was last updated on 13 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.5 MWwind farm
refusedstatus in REPD
13 September 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
26 August 2008Application submitted
22 November 2010Refused by the planning authority

Project details

Technology
wind farm
Capacity
19.5 MW
Status (REPD)
refused
Record last updated
13 September 2011
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Highland
Planning application reference
08/00386/FULCA
Turbines
13
Address (REPD)
Land at Mains of Durran Castletown Thurso
Council area (by location)
Highland
Time to decision
117 weeks
REPD reference
3070

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Castletown Wind Farmwind farm9.6application submitted1.8
Stainland Energy Storage Projectbattery storage49.9approved, not built7.2
Geiselittle Farmbattery storage49.9approved, not built7.3
Spittal Hillwind farm21refused on appeal7.6
Lyth Wind Farmwind farm24refused on appeal8.5
Lochend Holding, Barrock Wind Farmwind farm21application submitted8.5
Lochend Holding, Barrock Wind Farmbattery storage10application submitted8.5
Lochend Wind Farmwind farm9.2operational8.5
Buckies Farmbattery storage49.9application submitted8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5521, -3.385).