Energy Projects Near You

Lochend Wind Farm (9.2 MW)

Lochend Wind Farm is a 9.2 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 May 2017; the record was last updated on 19 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWwind farm
operationalstatus in REPD
19 May 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
29 July 2013Application submitted
31 March 2014Refused by the planning authority
27 June 2014Appeal lodged
11 December 2014Planning permission granted
11 December 2014Appeal allowed
15 May 2016Construction started
15 May 2017Operational

Project details

Technology
wind farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
19 May 2017
Operator or applicant
Wind Harvest
Planning authority
Highland
Planning application reference
13/02682/FUL
Appeal reference
PPA-270-2108
Turbines
4
Address (REPD)
Land 978M SE Of 2 Lochend Holding Barrock
Council area (by location)
Highland
Time to decision
71 weeks
REPD reference
4299

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lochend Holding, Barrock Wind Farmwind farm21application submitted<0.1
Lochend Holding, Barrock Wind Farmbattery storage10application submitted<0.1
Lyth Wind Farmwind farm24refused on appeal2.2
Scoolarywind farm120application withdrawn2.8
Hollandmey Renewable Energy Developmentsolar farm15approved, not built3.5
Hollandmey Renewable Energy Developmentwind farm50approved, not built3.5
Slickly Wind Farmwind farm49.9approved, not built3.9
Philips Mains, Meybattery storage300approved, not built4.9
Hill of Stroupster Windfarmwind farm29.9operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5951, -3.2629).