Hill of Stroupster Windfarm (29.9 MW)

Hill of Stroupster Windfarm is a 29.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 3 December 2015; the record was last updated on 18 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWwind farm
operationalstatus in REPD
18 January 2016record last updated
Highlandcouncil area

Planning timeline

DateStage
7 June 2005Application submitted
1 May 2006Refused by the planning authority
8 April 2010Planning permission granted
8 April 2010Appeal allowed
30 November 2013Construction started
3 December 2015Operational

Project details

Technology
wind farm
Capacity
29.9 MW
Status (REPD)
operational
Record last updated
18 January 2016
Operator or applicant
Greencoat UK Wind
Planning authority
Highland
Planning application reference
05/00273/FULCA
Appeal reference
06/00053/REFCA
Turbines
12
Address (REPD)
Stroupster, Caithness
Council area (by location)
Highland
Time to decision
252 weeks
REPD reference
4121

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scoolarywind farm120application withdrawn5.2
Slickly Wind Farmwind farm49.9approved, not built5.3
Tresdale Farm wind clusterwind farm6.9refused6.1
Hollandmey Renewable Energy Developmentwind farm50approved, not built6.3
Hollandmey Renewable Energy Developmentsolar farm15approved, not built6.3
Lyth Wind Farmwind farm24refused on appeal6.7
Hill of Stroupsterwind farm36application withdrawn7.5
Lochend Wind Farmwind farm9.2operational7.8
Lochend Holding, Barrock Wind Farmbattery storage10application submitted7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5793, -3.1324).