Energy Projects Near You

Tresdale Farm wind cluster (6.9 MW)

Tresdale Farm wind cluster is a 6.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 September 2017; the record was last updated on 4 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refusedstatus in REPD
4 October 2017record last updated
Highlandcouncil area

Planning timeline

DateStage
14 May 2015Application submitted
18 September 2017Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
4 October 2017
Operator or applicant
Coriolis Energy
Planning authority
Highland
Planning application reference
15/01261/FUL
Turbines
3
Turbine height
100 m
Address (REPD)
Land 760M SE Of Tresdale Farm, Canisbay, Wick
Council area (by location)
Highland
Time to decision
123 weeks
REPD reference
2896

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill of Stroupsterwind farm36application withdrawn2.9
Hollandmey Renewable Energy Developmentsolar farm15approved, not built5.9
Hollandmey Renewable Energy Developmentwind farm50approved, not built5.9
Hill of Stroupster Windfarmwind farm29.9operational6.1
Philips Mains, Meybattery storage300approved, not built6.4
Scoolarywind farm120application withdrawn6.7
Lochend Wind Farmwind farm9.2operational9.3
Lochend Holding, Barrock Wind Farmbattery storage10application submitted9.3
Lochend Holding, Barrock Wind Farmwind farm21application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.6336, -3.1211).