Hollandmey Renewable Energy Development (15 MW solar farm)

Hollandmey Renewable Energy Development is a 15 MW solar farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 September 2024, not yet built; the record was last updated on 1 October 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
approved, not builtstatus in REPD
1 October 2024record last updated
Highlandcouncil area

Planning timeline

DateStage
19 November 2021Application submitted
16 September 2024Section 36 consent granted (Scottish Ministers)
16 September 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
1 October 2024
Operator or applicant
Scottishpower Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003353
Address (REPD)
Land At Hollandmey Farm And Ph, Phillips Mains, Mey, Thurso,
Council area (by location)
Highland
Time to decision
147 weeks
REPD reference
10269

The scheme also includes 50 MW of wind farm, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Scoolarywind farm120application withdrawn1.8
Philips Mains, Meybattery storage300approved, not built2.5
Lochend Wind Farmwind farm9.2operational3.5
Lochend Holding, Barrock Wind Farmwind farm21application submitted3.5
Lochend Holding, Barrock Wind Farmbattery storage10application submitted3.5
Lyth Wind Farmwind farm24refused on appeal4.6
Slickly Wind Farmwind farm49.9approved, not built5.3
Tresdale Farm wind clusterwind farm6.9refused5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.6153, -3.2163).