Energy Projects Near You

Slickly Wind Farm (49.9 MW)

Slickly Wind Farm is a 49.9 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 August 2022, not yet built; the record was last updated on 24 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
approved, not builtstatus in REPD
24 October 2023record last updated
Highlandcouncil area

Planning timeline

DateStage
6 January 2020Application submitted
14 September 2021Appeal lodged
23 August 2022Planning permission granted
23 August 2022Appeal allowed
23 August 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
24 October 2023
Operator or applicant
Statkraft Wind UK Limited
Planning authority
Highland
Planning application reference
19/05624/FUL
Appeal reference
PPA-270-2256
Turbines
11
Turbine height
150 m
Address (REPD)
1650m E/O Slickly Croft, Lyth, Wick
Council area (by location)
Highland
Time to decision
137 weeks
Contracts for Difference
AR5
REPD reference
15099

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lyth Wind Farmwind farm24refused on appeal1.8
Scoolarywind farm120application withdrawn3.5
Lochend Holding, Barrock Wind Farmwind farm21application submitted3.9
Lochend Holding, Barrock Wind Farmbattery storage10application submitted3.9
Lochend Wind Farmwind farm9.2operational3.9
Hollandmey Renewable Energy Developmentwind farm50approved, not built5.3
Hollandmey Renewable Energy Developmentsolar farm15approved, not built5.3
Hill of Stroupster Windfarmwind farm29.9operational5.3
Philips Mains, Meybattery storage300approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5677, -3.2216).