Energy Projects Near You

Lyth Wind Farm (24 MW)

Lyth Wind Farm is a 24 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 20 May 2014; the record was last updated on 3 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
refused on appealstatus in REPD
3 July 2014record last updated
Highlandcouncil area

Planning timeline

DateStage
18 May 2013Application submitted
26 November 2013Refused by the planning authority
20 May 2014Appeal refused

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
refused on appeal
Record last updated
3 July 2014
Operator or applicant
Eurowind
Planning authority
Highland
Planning application reference
13/01832/FUL
Appeal reference
14/00004/REFCA
Turbines
10
Address (REPD)
Lyth near Wick in Caithness
Council area (by location)
Highland
Time to decision
27 weeks
REPD reference
4129

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Slickly Wind Farmwind farm49.9approved, not built1.8
Lochend Holding, Barrock Wind Farmwind farm21application submitted2.2
Lochend Holding, Barrock Wind Farmbattery storage10application submitted2.2
Lochend Wind Farmwind farm9.2operational2.2
Scoolarywind farm120application withdrawn3.0
Hollandmey Renewable Energy Developmentsolar farm15approved, not built4.6
Hollandmey Renewable Energy Developmentwind farm50approved, not built4.6
Philips Mains, Meybattery storage300approved, not built6.6
Hill of Stroupster Windfarmwind farm29.9operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5771, -3.2471).