Energy Projects Near You

Lochend Holding, Barrock Wind Farm (21 MW)

Lochend Holding, Barrock Wind Farm is a 21 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 July 2024, no decision recorded; the record was last updated on 30 August 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
application submittedmay be out of datestatus in REPD
30 August 2024record last updated
Highlandcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
26 July 2024Application submitted

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
application submitted
Record last updated
30 August 2024
Operator or applicant
Constantine Group Limited
Planning authority
Highland
Planning application reference
24/02641/FUL
Turbines
5
Turbine height
150 m
Address (REPD)
600M NE Of 10 Lochend Holding Barrock
Council area (by location)
Highland
Name in REPD
Lochend Holding, Barrock - Wind Farm
REPD reference
10656

The scheme also includes 10 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lochend Wind Farmwind farm9.2operational<0.1
Lyth Wind Farmwind farm24refused on appeal2.2
Scoolarywind farm120application withdrawn2.8
Hollandmey Renewable Energy Developmentsolar farm15approved, not built3.5
Hollandmey Renewable Energy Developmentwind farm50approved, not built3.5
Slickly Wind Farmwind farm49.9approved, not built3.9
Philips Mains, Meybattery storage300approved, not built5.0
Hill of Stroupster Windfarmwind farm29.9operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5949, -3.2631).