Energy Projects Near You

Wind Farm at Achlachan Windfarm (8.5 MW)

Wind Farm at Achlachan Windfarm is an 8.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 October 2025, not yet built; the record was last updated on 10 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWwind farm
approved, not builtstatus in REPD
10 November 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
29 April 2025Application submitted
10 October 2025Planning permission granted
10 October 2030Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
8.5 MW
Status (REPD)
approved, not built
Record last updated
10 November 2025
Operator or applicant
Whirlwind Renewables
Planning authority
Highland
Planning application reference
25/01306/FUL
Turbines
2
Turbine height
150 m
Address (REPD)
Achlachan Windfarm, Watten, Halkirk
Council area (by location)
Highland
Time to decision
23 weeks
Name in REPD
Achlachan Wind Farm 2, Watten - Wind Farm
REPD reference
18893

Earlier applications for this site

ApplicationMWSubmittedOutcome
Achlachan 2 Windfarm 15/01831/FUL7.511 May 2015refused 18 September 2015

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Achiesbattery storage162application submitted<0.1
Mybster Farm, Wattenbattery storage19.8application withdrawn2.7
Achlachan Wind Farmwind farm10operational2.8
Spittal Mains Quarrybattery storage49.9approved, not built3.2
Spittal Mains, Spittalbattery storage300application submitted3.2
Achlachan Wind Farm - Phase 2wind farm6.9abandoned3.6
Spittal Hillwind farm21refused on appeal4.4
Halsary Wind Farmwind farm34operational4.8
Bad a Cheo Wind Farmwind farm26.7operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.4702, -3.4803).